509 I-LINE SBS OFF GAS SYSTEM DESIGN AND APPORVAL KUMHO PETRO CHEM 2023.03~2023.09 E
508 FACTORY 2 RTO(80,000N㎥/hr 2ea) NEW INSTALLATION PROJECT KUMHO POLY CHEM 2023.03~2023.12 E / P / C
507 PILOT BUILDING OSBL AND ADJUSTMENT BUILDING INSTALLATION WORK LG CHEM 2023.03~2023.08 P / C
506 DETAILED DESIGN RELATED TO RELOCATION OF H-WWT1 WASTEWATER TREATMENT PLANT LOTTE CHEM 2023.03~2024.12 E
505 VCU INSTALLATION 2ND STAGE PROJECT S-OIL 2023.02~2024.03 E / P / C
504 ESTABLISHMENT OF INFRASTRUCTURE FOR NEW DAESAN PROJECT LOTTE CHEM 2023.02~2024.02 E / P / C
503 OFFSITE FACILITY IMPROVEMENT FOR FEEDSTOCK IMPORT S-OIL 2023.02~2024.03 E / P / C
502 PE PROCESS THROUGHPUT INCREASE DESIGN & APPROVALS GS CALTEX 2022.12~2023.04 E
501 RFCC FLARE GAS RECOVERY SYSTEM PROJECT DETAILED DESIGN SERVICE GS CALTEX 2022.11~2023.12 E
500 PIP(POTASSIUM ISOPRENOXIDE) 1,100MTPA PROJECT BASIC DESIGN LOTTE CHEM 2022.11~2023.12 E
499 VRHCR PROCESS 2ND STAGE MEMBRANE NEW CONSTRUCTION DETAILED DESIGN SERVICE GS CALTEX 2022.11~2024.03 E
498 DAESAN H2 56,000NM3/HR(42,500MTPA) PLANT PROJECT LG CHEM 2022.10~2024.08 E / P / C
497 10-3 SECTION PIPING SAFETY DIAGNOSIS SERVICE DAYONE ENERGY 2022.09~2022.11 E
496 10-3 SECTION PIPE RACK RESTORATION PLAN & STRUCTURAL SAFETY DIAGNOSIS SERVICE DAYONE ENERGY 2022.09~2022.12 E
495 SUS SAN(ACRYLONITRILE-STYRENE) 40MTPA REVAMPING PROJECT LOTTE CHEM 2022.09~2023.12 E / P / C
494 FEASIBILITY STUDY FOR BY-PRODUCT HYDROGEN SUPPLY PIPE AND WATER SUPPLY PIPE FOR HEAT RECOVERY GS CALTEX 2022.09~2022.12 E
493 DETAIL DESIGN SERVICE FOR LG CHEM STEAM SUPPLY PIPING INSTALLATION WORK HANWHA ENERGY 2022.08~2022.12 E
492 KKLC BPA WAREHOUSE DESIGN & APPROVAL KUMHO P&B CHEM 2022.08~2023.09 E
491 3rd FACTORY EXTERNAL PIPING PIPE RACK NEW PROJECT KUMHO P&B CHEM 2022.07~2024.05 E / P / C
490 DAESAN D PILOT PLANT PROJECT LG CHEM 2022.07~2023.08 E / P / C
489 TIAFENACIL PRODUCTION FACILITY BASIC DESIGN FARMHANNONG 2022.07~2022.09 E
488 P3 EXENSION BASIC DESIGN & TIC LX MMA 2022.07~2022.10 E
487 PBAT 3,000MTPA PROJECT LG CHEM 2022.07~2023.03 E / P / C
486 WASTE SYNTHETIC RESIN 7,920MTPA RECYLED OIL 4,752MTPA ENERGY CONVERSION PROJECT JEONYOUNG R.G.O 2022.07~2023.05 E / P / C
485 NCC T/A & STEAM NEWORK OPTIMIZATION PROJECT DESIGN XI C&A 2022.07~2023.02 E
484 LIVING RESOURCES RECOVERY CENTER INSTALLATION PROJECT HAMPYEONG-GUN, JEONNAM 2022.06~2023.06 P / C
483 BASIC & DETAIL DESIGN RELATED TO NO.1 PAREX PROCESS MVR PROJECT GS E&C 2022.06~2024.06 E
482 DESIGN AND PERMIT FOR STT(I) MIBK TANK USE CHANGE KUMHO P&B CHEM 2022.06~2022.12 E
481 NEW 250KTA HPEO REFINING FACILITY IN DAESAN EG-1 PLANT LOTTE CHEM 2022.06~2023.12 E / P / C
480 DETAILED DESIGN OF CRESOL STEAM SUPPLY PIPING INSTALLATION WORK HANWHA ENERGY 2022.05~2023.05 E