번호 Project Client Period Scope
140 DETAIL DESIGN FOR REVAMPING OF KUMHO MITSUI CHEM WASTE WATER TREATMENT PLANT Q-BIO TECH 2018.11~2019.07 E
139 PLANT 2 DEBOTTLENECKING PRE-ENGINEERING KUMHO POLY CHEM 2018.11~2019.01 E
138 DESIGN OF EXTERNAL PIPING GROUNDING PROJECT BETWEEN FACTORY AND CRUDE OIL STORAGE TEAM (ANTI-AGING) GS CALTEX 2018.09~2019.03 E
137 ACRYLIC IMPACT REINFORCING AGENT PRODUCTION PROCESS CONSTRUCTION WORK LG MMA 2018.07~2020.02 E / P / C
136 STT(SHORE TANK TERMINAL)I STORAGE INSTALLATION PROJECT KUMHO P&B CHEM 2018.07~2020.01 E / P / C
135 GS CALTEX SAR REVAMPING PROJECT PIPING 3D SCANNING & PERMIT DAEWOO E&C 2018.07~2019.06 E
134 EG CO2 DETAILED INVESTMENT DESIGN LG CHEM 2018.07~2019.05 E
133 GABLE EXPANSION PROJECT VERSUM ADM KOREA 2018.07~2019.05 E / P / C
132 YEOSU GROUP ENERGY UNDERGROUND STEAM PIPING GROUND DESIGN HYUNDAI E&C 2018.06~2019.09 E
131 MDI 60,000MTPA PLANT REVAMPING PROJECT KUMHO MITSUI CHEM 2018.06~2019.07 E / P / C
130 NEW INSTALLATION OF M-EC520A1/A2 SYSTEM KUMHO MITSUI CHEM 2018.06~2018.07 E / P / C
129 LG CHEM BPA 30,000MT DEBOTTLENECKING DESIGN PROJECT LG CHEM 2018.05~2019.04 E
128 HCC PETROLEUM RESIN PLANT PIPING CONSTRUCTION DESIGN HANWHA 2018.05~2018.11 E
127 SAP5 15,000 TON DBN PROJECT LG CHEM 2018.04~2019.06 E
126 DETAIL DESIGN OF M-EC520A1/A2/A3 EVAPORATOR KUMHO MITSUI CHEM 2018.04~2018.10 E
125 INVESTMENT PROJECT FOR PLANT MAINTENANCE OF YNCC #3 FACTORY IN 2018 YNCC 2018.04~2018.07 E
124 3D SCANNING WORK INSIDE #1 PX ADSORBENT TOWER S-OIL 2018.04~2018.05 E
123 BASIC DESIGN PACKAGE OF BANWOL PLANT FARMHANNONG 2018.04~2018.05 E
122 LG CHEM 6AA PROJECT SMS/PSM GS E&C 2018.03~2019.05 E
121 CA1 ELECTROLYZER PILOT FACILITY PROJECT LG CHEM 2018.03~2018.12 E / P / C
120 ALCHEMY PROJECT VERSUM MATERIALS PM KOREA 2018.02~2019.08 E / P / C
119 CONSTRUCTION OF DISPERSANT SEMI-MASS PRODUCTION FACILITY & SUSPENSION POLYMERIZATION PILOT RECONSTRUCTION LG MMA 2018.02~2018.05 E
118 LER(Ⅲ) PROJECT KUMHO P&B CHEM 2018.01~2019.06 E / P / C
117 GOJI PROJECT BASIC ENGINEERING AISA STABILIZERS 2018.01~2018.04 E
116 YEOSU LG CHEM SAP5 REVAMPING PROJECT SERVEONE 2017.11~2019.05 E
115 NUMAT PROJECT VERSUM MATERIALS 2017.11~2018.03 E / P / C
114 SSB & LET PROJECT KOREA PETRO CHEM 2017.10~2019.04 E
113 DETAIL DESIGN OF SK HYNIX M14 PHASE2B GAS PLANT PROJECT SK AIR GAS 2017.10~2018.11 E
112 INVESTMENT RELATED DESIGN SERVICE BESIDE INSTALLATION OF U-GA206D KUMHO MITSUI CHEM 2017.09~2017.11 E
111 3NE PROJECT GS E&C 2017.05~2019.04 E