119 | CM2 BASIC ENGINEERING DOCUMENT PACKAGE PROJECT | HANWHA CHEM | 2012.01~2012.02 | E |
118 | NEW PLANT WASTE HEAT RECOVERY SYSTEM INSTALLATION | KUMHO POLY CHEM | 2012.01~2013.07 | E / P / C |
117 | DESIGN FOR GS CALTEX VGOFCC(VGO FLUIDIZED CATALYTIC CRACKER) PROJECT SAPO-PIPE LINE (PIPING/ELEC./INSTR./CIVIL) | GS E&C | 2011.11~2013.04 | E |
116 | MIBK(DIISOBUTYL KETONE) 55KT CAPA UP PROJECT | KUMHO P&B CHEM | 2011.10~2012.10 | E / P / C |
115 | TAME(TERTIARY AMYL ETHER) PROJECT | GS E&C | 2011.10~2013.05 | E |
114 | BASIC CIVIL DESIGN AMONG HCC BELT CONVEYOR INSTALLATION PROJECT | HANWHA E&C | 2011.09~2012.03 | E / CS |
113 | Hx REFINE PROCESS IMPROVEMENT PROJECT | KOREA PETRO CHEM | 2011.09~2012.06 | E |
112 | #4 KERO MEROX(KEROSENE UNIT) PROJECT | GS E&C | 2011.08~2013.04 | E / PS / CS |
111 | KOREA SILICON 2ND STEAM LINE DETAILED DESIGN | YCOGEN | 2011.08~2012.04 | E |
110 | MDI(METHYLENE DIPHENYL ISOCYANATE) 50,000MT REVAMPING PROJECT | KUMHO MITSUI CHEM | 2011.07~2012.06 | E / P / C |
109 | DETAILED DESIGN FOR INSTALLATION OF LDPE SECONDARY EXTRUDER(FOR IT PROTECTION FILM) | LG CHEM | 2011.07~2011.12 | E |
108 | 4AA PROJECT CONSTRUCTION FIELD ENGINEERING (PIPING/ELEC./INSTR./CIVIL) | GS E&C | 2011.07~2012.05 | FE |
107 | INJU N20 PLANT & CYLINDER FILLING STATION DESIGN | LINDE KOREA | 2011.06~2012.06 | E / FE |
106 | NO.3 OFF-SITE SUBSTATION EXPANSION AND 2 OTHERS | GS CALTEX | 2011.05~2011.07 | E |
105 | NCC(NAPHTHA CRACKING CENTER) SCORE FURNACE REVAMPING PROJECT | LG CHEM DAESAN | 2011.04~2012.07 | E |
104 | KERO SPLITTER INSTALLATION PROJECT | GS CALTEX | 2011.03~2011.11 | E |
103 | GSC VGOFCC PROJECT DETAILED DESIGN(PIPING/INSTR./CIVIL) | GS E&C | 2011.03~2013.03 | E |
102 | MDA(METHYLENE DIPHENYL AMINE) REVAMPING PROJECT | KUMHO MITSUI CHEM | 2011.03~2011.07 | E / P / C |
101 | CA/EDC (CAUSTIC/ETHYLENE DICHLORIDE) PROJECT | LG CHEM | 2011.02~2011.07 | E |
100 | L-LDPE(LOW DENSITY POLYETHYLENE) PLANT ELASTOMER 13,000TON DEBOTTLENECK PROJECT | LG CHEM | 2011.01~2012.03 | E / P / C |
99 | STEAM PIPING DESIGN | HYUNDAI E&C | 2010.12~2012.06 | E |
98 | OTK NO.4 EXPANSION PROJECT | ISU E&C | 2010.12~2012.03 | E |
97 | INTRODUCTION OF TVR AND STEAM ACCUMULATOR | S-OIL | 2010.12~2011.07 | E / P / C |
96 | P-52141 CATALYST DEVELOPMENT UNIT ENGINEERING SERVICE | ALBEMARLE KOREA | 2010.09~2011.06 | E / PS / CS |
95 | HONAM PETRO CHEM HPEO(HIGH PURITY ETHYLENE OXIDE) PROJECT | LOTTE E&C | 2010.12~2012.10 | E / P / C |
94 | U-5500 PHENOL TREATMENT PROJECT | KUMHO P&B CHEM | 2010.11~2011.05 | E / P / C |
93 | LG CHEM 4AA PROJECT (MECHANICAL/PIPING/ELEC./INSTR./CIVIL DESIGN) | GS E&C | 2010.11~2012.07 | E / PS |
92 | PP PLANT EXTENSION PROJECT | LG CHEM | 2010.08~2011.09 | E |
91 | OIL REFINING 3TEAM ATMOSPHERE EMISSION UNIT IMPROVEMENT | GS CALTEX | 2010.08~2011.07 | E / PS |
90 | YEOSU COGENERATION PLANT DE-COMPRESS | YCOGEN | 2010.08~2011.05 | E / P / C |